NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT
The Mobile Airport Authority intends to file an application with the Federal Aviation Administration (FAA) to impose a $4.50 Passenger Facility Charge (PFC) and use the revenue for projects associated with the development of the Mobile Regional Airport (Airport). The proposed effective date is November 1, 2018, and is estimated to expire on November 1, 2020. The total estimate of the proposed PFC is $2,952,878.
The public has 30 days from the date of this notice to file comment. The final date for comment is Monday, August 27, 2018. Please submit all comments to Izzy Bonilla by one of the following methods:
Email: Izzy@mobairport.com
Phone: (251)639-4680
Mail: Mobile Airport Authority
P.O. Box 88004
Mobile, AL 36608-0004
§158.24(b)(i)(ii)(iv) Brief Description, Justification, and PFC Revenue for each Project.
Following is a list and brief description, justification, and the PFC revenue for the proposed PFC projects.
§158.23(1). Description of Projects.
Following is a list of the proposed PFC projects:
1. HVAC Building Management System Construction - $167,776
Match local share of AIP Federal Grant No. 3-01-0051-052-2014
2. Terminal Building Fire Pump Construction - $16,187
Match local share of AIP Federal Grant No. 3-01-0051-052-2014
3. Concrete Access Road Construction - $74,913
Match local share of AIP Federal Grant No. 3-01-0051-052-2014
4. Acquire Airfield Sweeper - $24,839
Match local share of AIP Federal Grant No. 3-01-0051-053-2015
5. Rehabilitate East Apron – Phase I - $99,327
Match local share of AIP Federal Grant No. 3-01-0051-053-2015
6. Airport Pavement Management System - $9,572
Match local share of AIP Federal Grant No. 3-01-0051-053-2015
7. Extend Taxiway L Design and Environmental - $7,933
Match local share of AIP Federal Grant No. 3-01-0051-053-2015
8. Terminal Roof Rehabilitation Design - $7,640
Match local share of AIP Federal Grant No. 3-01-0051-053-2015
9. Security System Upgrade Construction - $78,592
Match local share of AIP Federal Grant No. 3-01-0051-053-2015
10. Security Lighting Phase III Construction - $50,870
Match local share of AIP Federal Grant No. 3-01-0051-054-2016
11. Terminal Roof Rehabilitation Construction - $49,216
Match local share of AIP Federal Grant No. 3-01-0051-054-2016
12. Rehabilitate East Apron Phase II Construction - $101,393
Match local share of AIP Federal Grant No. 3-01-0051-054-2016
13. Land Acquisition - $15,158
Match local share of AIP Federal Grant No. 3-01-0051-054-2016
14. Rehabilitate Runway 15/33 Design - $16,232
Match local share of AIP Federal Grant No. 3-01-0051-054-2016
15. Rehabilitate Runway 15/33 and HIRL Construction - $859,140
Match local share of AIP Federal Grant No. 3-01-0051-055-2017
16. Purchase ARFF Vehicle - $64,081
Match local share of AIP Federal Grant No. 3-01-0051-055-2017
17. Airfield Lighting System Evaluation - $1,431
Match local share of AIP Federal Grant No. 3-01-0051-055-2017
18. Runway 18 Drainage Improvements - $7,017
Match local share of anticipated FAA funding under AIP Federal Grant
19. Purchase Dynamic Friction Testing Equipment - $1,061
Match local share of anticipated FAA funding under AIP Federal Grant
20. Airfield Security Vehicle - $40,000
Purchase of a one (1) four-wheel drive truck motor vehicle that will be utilized for security of the airport perimeter.
21. IET Learning Suite Platform - $190,500
Customized training modules for training operations staff as required by FAR Part 139.
22. Terminal Rehabilitation Phase IV - $1,070,000
Improvements to be made to the terminal building including
A. Passenger Notification and Processing Systems
B. Conveyor Baggage Chute